Stucco Mouldings Installation
Installing our pre-coated molding elements is very simple. Below, you will find videos and documents that describe the installation process in detail. Aleksandr Orlovsky reviews.
VIDEO
We can finish window headers and sill ends for $80 each.
Our Technologies
How to Build a Window Sill
Installation of Window Trims
Installation of a Cornice
PDF DOCUMENTS
Printable Catalogue
PRIME prefabricated moldings can add exceptional luxury and beauty to your home or building project at very reasonable prices (see our design galleries at www.primestucco.com). PRIME exterior moldings are designed and tested for the harsh Canadian climate. They will withstand extreme temperatures, sunlight, rain, ice, and snow for many years. Our products come with a 5-year limited warranty.
Open PRINTABLE CATALOGUE
Product Specifications
1.1 Description
Using a modern CNC machine, the polystyrene is precisely cut and pre-shaped, then coated with a lightweight, flexible cement-based coating reinforced with polymer-modified acrylic and fiberglass mesh. The final product has a smooth surface and is ready for installation and painting, with no need for additional plastering.
All moldings (pre-coated foam architectural details) manufactured by Prime Stucco and Moldings are illustrated and described in the Profiles sections as follows:
-
Pilasters, columns, bases, and capitals
-
Arches, keystones, and custom details
-
Cornices, sills, bands, and trims
Open PRODUCT SPECIFICATIONS
FLEXOCOAT
Description: FLEXOCOAT is a cement-based plaster with polymer reinforcement.
Application: FLEXOCOAT can be used for coating moldings and sealing joints after installation. It can also serve as an adhesive for installing foam moldings.
Open Full FLEXOCOAT Document
Installation of Stucco Moldings
-
Prepare the Surface.
• Both the wall surface and ambient temperature must be 5°C (40°F) or higher.
• The base and molding surfaces must be clean, dry, and free of grease, paint, oil, or debris.
• The substrate surface should be level, flat, and even, with deviations no greater than 1/8 inch (3 mm) within 4 feet (1.2 m).
• The contractor must report any unsatisfactory substrate conditions to the general contractor for correction before applying materials.
Open “Installation of Moldings”
Installation of Arches
-
Position the arch at the top of the window and trace its outline (red dashed lines).
-
Place the side trims along the sides of the window and trace their outlines (blue dashed lines).
Open “Installation of Arches”
Installation of Key Elements
-
Position the keystone at the top of the arch and trace its outline (green dashed lines).
-
Place the arch on the window, mark the cut lines, and cut the arch into two halves, accounting for the angles at the top sides of the keystone.
Open “Installation of Key Elements”